Page County ARPA Funds
Democrats Make a Tangible Impact in our Daily Lives by Delivering Meaningful Outcomes
Were you aware that locally, Page County received approximately $5 million thanks to the Biden administration and the Democrats’ American Rescue Plan?
Here’s the detailed breakdown:
1 | ARPA Funding Decisions | 6/18/2024 | |||||
---|---|---|---|---|---|---|---|
2 | REVENUES: | ||||||
3 | ARPA | FY 21-22 | $ 2,514,940.00 | ||||
5 | FY 22-23 | $ 2,514,940.00 | |||||
6 | Total Funding $5,029,880.00 | ||||||
7 | Project: | Paid to Date | Status | Project Balance Remaining/ Allocation Remaining | |||
8 | Hazard Pay | ||||||
9 | Year 1 | $ 51,312 | Paid | $ - | |||
10 | Year 2 | $ 54,385 | Paid | $ - | |||
11 | Legal Fees/Town Attorney Consultation | $ 5,052 | Paid to date | $ 35,000 | |||
12 | Administration/Single Audit | $ - | Allocated | $ 5,000 | |||
13 | Electric Upgrades- Mechanic Street Lot | $ 11,585 | Paid | $ - | |||
14 | Greenway Extension | $ 12,100 | Paid | $ - | |||
15 | Greenway Extension | $ 2,000 | Paid | $ - | |||
16 | Greenway Extension | $ 6,400 | Paid | $ - | |||
17 | Phase 2 of Feasibility Study for Greenway Extension | $ 23,100 | Paid | $ - | |||
18 | Yager Spring- Task 1 | $ 20,950 | Pd to date $20950. | $ 19,050 | |||
19 | Hawksbill Greenway Foundation | ($ 20,000) | Foundation Contribution | $ - | |||
20 | Parks and Rec Dump Trailer and Truck | $ 64,453 | Paid | $ - | |||
21 | Parks Security Camera Replacement | $ 34,001 | Paid | $ - | |||
22 | Electronic Metering- downpayment | $ 561,328 | Paid | Financing for Proj. Remainder | |||
23 | 4 Police Vehicles- Sheehy Ford | $ 198,421 | Paid | $ - | |||
24 | Page Valley News Advertising - Year 1 | $ 7,072 | Paid | $ - | |||
25 | Page Valley News Advertising - Year 2 | $ 7,072 | Paid | $ - | |||
26 | Page Valley News Advertising - Year 3 | $ 7,072 | Paid | $ - | |||
27 | Page Valley News Advertising - Year 4 | $ - | allocated | $ 7,072 | |||
28 | Police Radios | $ 128,255 | |||||
29 | Police Radios- Removed for Grant | ($ 128,255) | |||||
30 | Police Equipment Other and upfits | $ 48,129 | |||||
31 | Police Veh & Upfit | $ 53,862 | |||||
32 | Police Equipment (body cams/tasers, equip) | $ 120,009 | Paid | $ - | |||
33 | Imagination Station Replacement | $ 365,796 | Paid | $ - | |||
34 | Town Hall and Visitor Center HVAC | $ 40,202 | Paid | $ - | |||
35 | West Lu Lift Station *** See Notation Below | $ 791,576 | Paid | ||||
36 | BIDS = 1.1 MIL. / remainder from proffer fees | ||||||
37 | $791576 paid to date from ARPA , remainder was from Fac Fees TOTAL = 1,072,362 | ||||||
38 | Sewer Vac Truck | $ 345,147 | Paid | $ - | |||
39 | Sewer smoke equipment | $ 4,175 | Paid | $ - | |||
40 | Street Sweeper | $ 259,890 | Paid | $ - | |||
41 | Sewer Line Inv. Equipment(camera) | $ 108,828 | Paid | $ - | |||
42 | Finished Water Pump Replacement | $ 168,825 | Paid | $ 41,735 | |||
43 | Paid $168,825 | complete by 6/30 | |||||
D | E | F | G | ||||
44 | Raw Water Pump Replacement | $ 61,382 | Complete/Paid | ||||
45 | Display Cabinet- Lobby Artifacts | $ 2,335 | Paid | 0 | |||
46 | Depot HVAC- Emergency Repair | $ 19,970 | Paid | $ - | |||
47 | Spare Influent pump | $ 36,240 | Paid | $ - | |||
48 | Water Treatment Plant Storage Shed | $ 8,999 | Paid | $ - | |||
49 | IT Contract Overage Fy 23 | $ - | Paid | $ - | |||
50 | Sludge Spreader- WWTP | $ 45,000 | Paid | $ - | |||
51 | Recycle Trailers | $ 3,000 | Paid | $ - | |||
52 | SCADA Upgrade | $ 132,926 | PAID | $ - | |||
53 | allocated $130,000/ remainging from Blue Ridge Bank financing | complete by 6/30 | |||||
54 | Treasurer's Office Printers | $ 924 | Paid | $ - | |||
55 | Luray Parks Association- Carrillion Lighting/Electric | $ 10,000 | Paid | $ - | |||
56 | Dean Park Infield Mix & Controller | $ 19,166 | Paid | $ - | |||
57 | Daughter of the Stars Farmers Market | $ 2,500 | Paid | $ - | |||
58 | Sewer Lining- Watch & Warrant- Emergency Repairs | $ 26,750 | Paid | $ - | |||
59 | Contributions- Living Legacy, Page One, Arise | $ 15,000 | Paid | $ - | |||
60 | Rosser, Terrace, Cave Hill, Stover Infrastructure | $ 145,257 | Approved | $ - | |||
61 | Storage Building at Dean Park | $ 39,481 | paid to date | $ - | |||
62 | Pickleball Court Allocation- RFP Maximum- $200K APPROVED | $ 16,020 | paid to date | $ 186,830 | |||
63 | Influent Screening- $128,900 Paid from Sewer Fund | $ - | Paid- Sewer Fund | $ - | |||
64 | Oxidation Ditch Pump- $ 238,279 Paid from Sewer Fund | $ - | Paid- Sewer Fund | $ - | |||
65 | Luray Fire Dept- Airpack Contributions | $ 22,000 | Approved | $ - | |||
66 | Ruffner Plaza Sail Shade | $ 152,733 | Approved | $ 50,267 | |||
67 | |||||||
68 | Friends of the Shenandoah River | $ 2,500 | Approved | $ - | |||
69 | Influent Pump Station Control Panel Upgrade- Sewer Project | $ - | Approved | $ 160,000 | |||
70 | Replacement of Several Sewer Segments - Sewer Project | $ 4,178 | Approved | $ 100,823 | |||
71 | WWTP System & Plant Upgrades | $ - | Approved | $ 140,000 | |||
72 | Hite Spring Improvements- Water Project | $ 23,590 | Approved | $ 136,410 | |||
73 | VRT Transportation Study | Proposed | $ 5,000 | ||||
74 | $ 4,142,694 | ||||||
75 | Committed/Paid | ||||||
76 | Total Funding | $ 5,029,880 | $ 887,186 | Work In Progress: | |||
77 | Cash Fund Balance | $ 937,181 | |||||
78 | Reserved for Work in Progress and Proposed Projects | $ 887,186 | $ 887,186 | ||||
79 | |||||||
80 | Unallocated | $ 49,995 |